Area - 281 Acres
Civil
• Design Cslt - M/s ProMag
• Supr Cslt - M/s NVEC
• Contr - M/s TTC
• Start date - Jul 17
• Completion date - Aug 22
Elec
• Design Cslt - M/s ProMag
• Contr - M/s Descon Engr
• Start date - Mar 20
• Completion date - Jan 23
Gas
• Design Cslt - SNGPL P&D Br
• Contr - M/s ZGC
• Start date - Nov 19
• Completion date - Sep 21
• Sec C was completed and bounded by Jinnah Avenue 250’ wide and Edhi & Abbasi Avenue 150’ wide.
• Civ Infra works completed and Possession was opened in Nov 2021.
• U/G Elec network is being laid for energization.
• Internal Sui Gas network has been completed, Testing and commissioning is in progress.
• Currently 17 houses are under const.
• Pelican Mall located in same sector, which is 1st Comm Mall of DHAB also in under const phase.
• Const of Sec Mosque will start shortly.
• Sec parks are being dev and other basic amenities are also planned a/w const of commercial shops to meet basic req of residents.